Project size / # of tons of sand | 25 ton |
30 ton |
50 ton |
75 ton |
100 ton |
|
# sheets of 5/8" CDX plywood | 6 | 8 | 10 | 12 | 16 | |
# 12' long 2X4 (construction grade) | 22 | 30 | 36 | 44 | 60 | |
# of pounds of 8 d common nails | 5 | 5 | 10 | 10 | 10 | |
# of pounds of 16d duplex nails | 5 | 10 | 10 | 10 | 10 | |
# days - front-end loader | 1 | 1 | 1 | 1 | 2 | |
# of days - compactor | 1 | 1 | 1 | 1 | 2 | |
# of days - circular saw w/blade and ext. cord | 1 | 1 | 1 | 1 | 1 | |
# of laborers # of days |
2 1 |
3 1 |
4 1 |
4 1 |
4 2 |
Sand: Sand must be on site at 10:00 AM on our first scheduled day of construction. If you are interested in supplying sand our specifications have been included on the attached "Sand sheet", simply send this sheet to local sand suppliers.
Lumber: Lumber must be on site at 8:00 AM on our first scheduled day of construction.
Equipment:Laborers: Laborers with shovels must be on site at 10:00 AM on our first scheduled day of construction